Quantitative Aptitude :: Time and Work Problems And Answers

8. 36 workers can reap a field in 6 days. If the work is to be completed in 4 days, the extra workers required are

A. 10 B. 25
C. 18 D. 15
Answer & Explanation

Answer: Option C

Explanation:
M1D1 = M2D2
36(6)=X(4)
=54
Extra required workers are 54-36=18


Write your comments here:
Name *:     Email:

Who are all can get the advantages from this Time and Work Question and Answers section?

Those are all planning for any competitive examinations can use this segment to enhance their abilities.

Time and Work questions and answers pdf

Where Time and Work is Used?

Time and Work is used to improve individual's awareness about the use of computers at workplace. Here you will be able to practice and learn All Non Verbal Figures along with Explanations (Questions with Answers) which will improve your Math skills. Also helps to write the Bank, Competitive Examination (like IBPS, LIC AAO, MAT, CAT, GRE) and other Government entrance test (SSC CGL, CDS, NDA, SCRA Railway Apprentice Exams, RRB, RBI ACIO).

How shall I Download Time and Work questions and solutions with explanations?

IndianStudyHub is providing all Time and Work questions and answers along with detailed explanation in an easy and understandable way. They are explained in elaborated manner to get clear subject knowledge.

How to get knowledge for using computers effectively?

You will be able to answer all kind of questions based on Time and Work by practicing exercises given in this Computer Knowledge section.

How to get concepts for Time and Work

One can get all the concepts explained in a detailed manner in Time and Work section.

Where did all the important topics of reasoning are explained in IndianStudyHub.in?

Quantitative Aptitude Questions and Answers

Logical Reasoning Questions and Answers

Verbal Abilitie Questions and Answers

Basic Computer Knowledge

Indian Study Hub